Which columns make the index useful?

Use stable asset and document identifiers, then add status and evidence fields. Keep superseded procedures and corrected records traceable.

Commissioning records index
FieldWhy it mattersExample status
AssetLinks record to equipmentGEN-01
ProcedureShows approved methodCurrent revision
ResultRecords outcomeReceived for review
DeficiencyLinks open issueOpen or closed
LocationFinds evidenceControlled folder

Sources: ASHRAE: Commissioning resources and Standard 202-2024, US Department of Energy: Commissioning Process for Federal Facilities

How should a record status be written?

Use distinct statuses such as missing, received, under review, accepted, rejected or superseded when the project process permits them. Do not use complete when a reviewer has not accepted the evidence.

Sources: ASHRAE: Commissioning resources and Standard 202-2024

What is the handover test?

A handover index should let the receiving team find the approved record for every required asset and identify remaining deficiencies. It does not create evidence that was never produced.

Common questions

What else should the bid team know?

Does a documentation pack approve a test?

No. The commissioning professional and responsible engineers approve procedures, criteria and acceptance decisions.

Are commissioning levels universal?

No. Project and client documents define the meaning and gate for levels. Use the approved commissioning plan.

Can a missing acceptance criterion be invented?

No. Record it as an open input and obtain the approved criterion from the responsible technical reviewer.

Primary sources

  1. Commissioning resources and Standard 202-2024ASHRAE
  2. Commissioning Process for Federal FacilitiesUS Department of Energy
  3. Lessons Learned from Tier Certification of Constructed FacilitiesUptime Institute