What belongs in the witness record?

Illustrative example. A generator startup observation should reference the approved procedure, selected unit and actual result.

Witness record fields
FieldCheck
AssetExact equipment ID
ProcedureApproved revision
WitnessNamed role
ResultObserved value and evidence
Open issueDeficiency reference

Who controls the process?

The responsible commissioning professional approves test sequences, acceptance criteria and results. Only the registered engineer on the job performs engineering sign-off.

ASHRAE Standard 202 describes principal commissioning roles and documentation requirements.

Sources: ASHRAE: Commissioning resources and Standard 202-2024

Common questions

What else should the bid team know?

Is a witness point always a hold point?

No. The project ITP defines the difference.

Can a blank signature imply acceptance?

No. Record the actual disposition and owner.

Primary sources

  1. Commissioning resources and Standard 202-2024ASHRAE
  2. Commissioning Process for Federal FacilitiesUS Department of Energy
  3. Lessons Learned from Tier Certification of Constructed FacilitiesUptime Institute